Fire at ASC

WE'RE BACK!
After 528 days, ASC is back in business in our original offices!

Go straight to the latest update...

At about 9:30 on Saturday morning July 29, 2006, a maintenance supervisor working on a landscaping project in front of the building which houses ASC's offices noticed something peculiar as he glanced up toward the second floor windows. Moments later one of the windows shattered and he could see that the building was on fire. He called 911 and by 9:40 the first firefighters were on the scene.

ASC personnel were notified and began arriving shortly afterward. More than 40 firefighters from four surrounding communities battled the blaze for approximately 90 minutes.

Fire damage is evident on the rear facade.
ASC offices are just to the left of burn area on third floor.
ASC Entryway

ASC 'South'
Our new headquarters.

Not long after, IT personnel, using a wireless laptop, were able to access ASC's offsite web server and re-establish our websites.

Joe transfers hosting of ASC's websites to our offsite servers in Florida
Server Evacuation
Concern but no panic as ASC 'South' is established

Some five hours later, at about 3:30 pm, fire officials declared the building to be somewhat stable and allowed very limited access to tenants. A team of 11 ASC employees entered the suite and began rescuing equipment. They braved temperatures well over 120 degrees (it was almost 90 degrees on Saturday), darkness (power had been cut off), smoke, soot, broken glass, and stress (building officials determined there was significant damage to the structure and advised the everyone evacuate as soon as possible). During their brief time inside, they dismantled the entire server room (10 large computers), grabbed up more than 20 laptops and other PCs, and secured other equipment and data. The building was then locked and remained guarded while officials investigated the origin of the fire.

Since the fires origin was below ASC's suite, the offices did not sustain any water damage. However, it was said that the fire flashed to more than 1200 degrees during its peak, and it was fortunate that all the servers were still intact and operable. While the team was rescuing equipment and securing the premises, other personnel found temporary office space, namely three suites in a nearby extended residence hotel about a quarter mile from ASC.

By 6:00 pm, a server room was set up in one of the hotel suites, just hours after the team hauled them out of ASC, and by 3:00 am many mission-critical services such as e-mail, some database servers, and other links were re-established. A single laptop served as a router for all of our network traffic.

Makeshift Data Center

ASC IT personnel worked throughout the night to set up and monitor the remaining servers. They battled exhaustion, as well as the limited bandwidth and power resources of the hotel. They were also faced with the daunting task of turning the suites into a makeshift office for employees come Monday morning.

Meanwhile, ASC officials were already looking into both short-term and long-term office space alternatives, in case the damaged building remained unusable for an extended period of time.

Core ASC services restored just 36 hours after rescue from fire -damaged suite

On Sunday morning, July 30, building officials allowed tenants to reenter their suites for a brief time. Power had been restored and more peripheral equipment and personal items were removed. Another security check on all hard and soft data was performed as well.

All ASC clients were contacted by e-mail by 11:00 am and told of our predicament. IT personnel continued to re-establish services, and by late afternoon almost all of ASC capabilities were back on line, albeit in a limited capacity, less than 36 hours after the fire was first reported. These services included e-mail, and web access to e-mail, all ASC websites, CustomerFirst and SalesFirst (our client contact systems, including web access to each), PowerSeller development and QA, PowerLender Development & QA, our general operation database and related servers.

By 8:00 am on Monday, July 31, ASC will be open for business as usual. Please excuse us if you experience any interruption in your support services.

This unfortunate occurrence could have happened to any company at any time, however, a few important factors greatly changed the outcome. First and foremost, the heroic efforts by ASC personnel turned misfortune on its ear. The result of their sweat and toil on Saturday and Sunday was truly amazing but not at all surprising. Traditionally we don't really seem to need the IT Department until something goes wrong. When it did in a very large way on Saturday, they performed as they always do, quietly, efficiently, and superbly. Thank you. And thanks to everyone else who helped in ways big and small this weekend.

The second factor was that ASC had a disaster recovery plan in place and it played a vital role in the quick recovery. Approximately two years ago, ASC underwent an SAS-70 audit. It isn't required, and not many companies have gone through it. The recent hurricane disasters in the Gulf Region have brought a little more attention to it, but ASC had the foresight to have it and practice it.

Off-site data storage, redundant servers, a secured and monitored server room, and detailed recovery plans were just a few of the practices that helped in our speedy recovery. IT personnel, upon being notified of the fire, were able to visually monitor the offices via remote video cameras. Even before we arrived inside the suite, the remote temperature monitors told us that the sensitive servers did not suffer excessive exposure to heat, and, as we later learned, temperature and smoke sensors in our alarm system indicated fire just about the time it was discovered.

It was determined that the fire began approximately 7:00 am Saturday morning. Our last hot backup to the offsite servers in Florida was completed a little after 7:30 on Friday night.

We cannot stress enough the importance of this plan to ASC's well being. Monday morning is obvious proof of this.
The third factor would be the resilience of ASC ownership and management. This proud company, who recently celebrated its 28th anniversary, came together as it always has to overcome a devastating disaster. Not an ounce of despair or self-pity was displayed or shared by anyone. After helplessly watching their business seemingly go up in flames, the leaders of ASC quickly rolled up their sleeves and went about fixing it with the same attitude and determination that got them there in the first place.

The last factor is our valued customers. The only concern we had this weekend was the hope that we can deliver the same quality of service to you as you have come to expect from us. We thank you for your understanding and patience. We will continue to provide further information as soon as possible.

Upon being informed that her Dads business had caught fire and was damaged, 11-year old Kate Liston, daughter of ASC president Tim Liston, wrote the following in an e-mail to console him: Hi daddy it's katie i am sorry about the building. If you have a fundraiser i'll sell raffle tickets!!:)


Timeline

Saturday, July 29, 2006

9:30 am--Fire reported in ASC's office building.
9:40 am--Fire crews arrive.
10:30 am--First ASC personnel notified of fire. Word is spread.
11:00 am--First ASC personnel on site. Suite is monitored via remote webcam. Reports relayed via cell phone to fire site.
11:20 am--Fire doused.
11:30 am--Alternate office site search begins. Hotel suite secured for temporary office. Offsite servers contacted via wireless website restored.
3:30 pm--ASC personnel carry out nearly 40 servers, PCs and laptops from suite.
4:00 pm--ASC main website tells of and displays images of damaged suites
5:00 pm--ASC staff notified by phone.
6:00 pm--Server room established in hotel suite.
IT staff establishes round-the-clock presence to monitor systems.


Sunday July 30, 2006

3:00 am--Mission-critical components such as e-mail and customer contact capabilities restored.
9:00 am--Return to damaged suite to salvage additional resources and to secure premises. Power restored to damaged suite. Ohio Fire Marshal investigates damage severity.
ASC suite suffers smoke and light soot damage, however building structure is main issue.
11:00 am--All ASC customers are informed of the situation via e-mail.
6:00 pm--Round-the-clock work results in nearly all services being restored in limited capacity including:

  • E-mail, and web access to e-mail
  • ASC websites
  • CustomerFirst and SalesFirst (our client contact systems, including web access to each),
  • PowerSeller Development & QA
  • PowerLender Development & QA
  • General operation database and related servers.

Monday, July 31, 2006

ASC opens for business as usual.

Core ASC personnel report to hotel suites to begin work. Schedules and personnel rotations are created.

Many ASC folks work from home as well. This practice was established a while ago for two reasons. To study the feasibility of telecommuting at ASC and, in part, to put in play some of our disaster/backup plan. This idea has been a great success at ASC, especially with programmers, and QA people. This has saved ASC and environmental resources, as well as improved morale. ASC has been very active in experimenting with a virtual office scenario for portions of its workforce.

The removal of supplies and equipment continues at the damages ASC site as limited access is granted.
Search for temporary and permanent office space continues.

Wireless bandwidth is discovered to fluctuate with the ascending and descending of a nearby elevator. Larger antennae quickly remedy the problem.


Tuesday, August 1, 2006

Administration, PowerSeller, PowerLender, and Sales were all hard at work on Monday

Another day at the office. ASC handles support calls, programming issues and sales follow-up calls as it typically would on any other day.

More insurance and landlord fun follows as the details are being sorted out.

ASC persons not directly involved in fire recovery should also be commended for making the best of the situation. Working on beds and card tables while taking support calls isn't easy, especially when there are five persons in a standard hotel room.

IT continues its outstanding job providing more services and access to necessary databases.

Office sites are visited and evaluated on technical, cost, size, and geographic criteria.


Wednesday, August 2, 2006

Life gets better all the time at ASC South. The routines are setting in and things run much more smoothly.

A team investigates area training facilities in order to remain on promised schedules.

The sales team continues their prospecting efforts in spite of the cramped conditions. A scheduled web demo goes on as planned, with the demo driver at home and the sales rep at the hotel.

IT staff maintains their round-the-clock vigil over a makeshift network/data infrastructure. This is the fifth day of temperatures well above 90 degrees, record power-use levels, and rolling blackouts.
All the while, ASC has received many e-mails from clients expressing not only their sympathy for what has happened, buy also their amazement at how quickly we have recovered.

Below are a few examples:

  • Sorry to hear about the fire and hope everything gets back to normal for you soon. It's amazing you are up and running so soon. ---Denise Green, Accurate Document
  • We are so sorry to hear about your misfortune. Our resources will be available to accommodate ASC in any way that we can. Thanks for keeping us in the loop. --Timothy Walker, Freddie Mac
  • We are very sorry to hear about the fire in your building. We are happy to hear no one was hurt. Here we were worried about the flooding in your area! Kudos to all of you at ASC for your quick response and dedication to getting everything back up and running. We know it takes a lot of work and team effort to make a disaster recovery plan work when put to the test. ---The Gang at Severn Bank
  • I am so sorry to hear about the fire. It is amazing that I was able to login to our website today. It just goes to show what great people are at ASC. I just wanted to send a little message to let everyone at ASC know that we are behind you 110%. I am happy that everyone is OK. Being a longstanding customer of ASC I know how committed you are to customer service. I know it won't take very long to be back on your feet again. If there is anything that we can do just ask! ---Dawn Day, Chelsea Groton
  • We also understand that we were the topic of conversation at KeyBank's business unit manager's meeting. They call PowerLender Support Manager Tom Osborne me at 8:30 yesterday morning and were very surprised we were up and running.
  • To: Jay (McKee, PowerSeller Client Services Manager), This just blows us away. Horrendous occurrence but remarkable resilience, efficiency and team spirit displayed by ASC people. Our hearts go out to you all as you battle through this very difficult time. -- Nancy O'Loan, World Savings
  • ASC Team: Congrats on the smooth execution of your recovery plans! Best wishes from your friends at VMP
  • John: I have been following the ASC website on the fire status from the day Lori notified me of the unfortunate event. While feeling sorry for the loss of property and serious interruption to operations, I could only admire the strength with which ASC started focusing on customer support immediately after the fire. The manner in which the ASC team adjusted to the situation is quite extraordinary. As someone who has been associated with ASC for several years, I feel the rebound is due to the strong leadership, positive culture and work ethic at ASC (at the same accepting the role of SAS-70 audit and disaster recovery processes in place). I am confident you will come out of this phase much stronger. I again wish the team at ASC all the very best in the recovery phase. My only disappointment is not being able to help at your hour of need. Please let me know if at all I can do something. -- Kiran Prathapa, Trilogix Software Solutions

Thursday, August 3, 2006

Mobile electronics cleaning lab parked outside of ASC
An electronics cleaning lab appears at the ASC fire site and begins cleaning PCs and other vital ASC equipment. The lab, which is essentially a customized mobile home, contains various electronic, chemical and gas-oriented devices for cleaning and deodorizing equipment. They completely disassemble each PC removing the motherboard and cleaning both sides, removing the power supplies and taking them apart to clean each piece, removing CD trays to swab them clean etc. Each unit takes about 2+ hours to clean. The service said our servers took "a lot of smoke". We suspected they were the machines least affected by the smoke but that was not the case.

Every piece of electronic equipment we own will be cleaned unless it was not in the building at the time of the fire or we deem it not worth cleaning and decide to just replace it. That means every PC, server, laptop, printer, copier, phone, PBX cabinet, monitor, firewall, router, LAN switch, projector, etc., will be tagged with a bar code, cleaned either in the mobile lab or back at their cleaning facility and either returned to us for immediate use or stored in a climate controlled facility until it is needed.

Another office space was visited today.

There is some interesting new telephone technology was reviewed as well, in case our existing system cannot be used.


Friday, August 4, 2006

ASC holds its first full staff meeting since the fire. Policies and procedures for working in our temporary space are reviewed. Options for the future are presented. Tim implores all of us to remain on task, and promises things will get better.

More potential office sites are visited. Sales performs a web demonstrations as scheduled. It goes very well.

A small group of ASC employees, working in half-hour increments, spent the majority of the day Friday removing the remaining electronic and other items from the damaged office suite. In all, they removed approximately 350-400 pieces of equipment, including all phones, laser printers and even the copier. It was cataloged and tagged by the cleaning service and then loaded onto a truck. They began about 9:00 am and finished loading about 8:00 pm. Most of this will be cleaned and stored until it is needed.


Saturday, August 5, 2006

Electronic cleaning continues, as IT personnel swap out servers and rely on backups. Most of the equipment at the hotel has been cleaned including several of core servers. Most laptops and workstations are cleaned and back in their respective rooms. This includes developer PCs for use at home. By Sunday, items such as our laser printer, portable projector, and monitors should be complete.


Sunday, August 6, 2006

All items in the hotel, including many individual PCs are now clean and will be returned. The mobile lab will remain on site to clean the few remaining items which are being brought in on Monday.


Monday, August 7, 2006

The electronic restoration service has cleaned, wrapped and stored about half of the hardware that was removed on Friday. They expect to be done by the end of a week from Friday.

Of all the equipment that was rescued from the damages suite so far, only two known problems surfaced, and they were easily remedied. The only question which remains of the hardware is how the fire affected the life expectancy of each piece. But, so far, so good.

An additional PC station was setup for the sales department. A direct mailing to prospects, planned before the fire, will go out within the week. Marketing plans for the upcoming MBA National Convention are continuing.

ASC technical people are booking flights to travel to clients sites.


Tuesday, August 8, 2006

No word on our future office space plans, but Tim has been hard at work looking for an appropriate site while dealing with insurance and tenant issues. Some things we do now know. We will be in some form of temporary space for at least six months.

In review of ASC's complex business insurance policies, it was determined that ASC's coverage in all aspects was ample. This was and remains an important factor in maintaining the high level of customer services that are delivered.

Support with a smile!
Courtesy of PowerSeller

What's a support department
without a whiteboard?

Wednesday, August 9, 2006

Life continues as best it can at ASC South. We would like to take this time to thank all our clients, vendors and friends for all their well-wishes, gifts, and words of encouragement. We are truly fortunate to be involved with such kind and caring people, thank you.

Schedules are determined so that ASC personnel can return to the damage suite to retrieve any personal effects prior to the arrival of the clean-up service.

More capabilities become available to us each day, allowing us to move a little closer to operational normalcy.


Thursday, August 10, 2006

Sharing a cellphone...sharing a single printer...sharing a room with six people...having to knock or call to be let in...hearing someone else's ringtone, over and over again, in your sleep...assigned bathrooms...working on beds, coffee tables, TV trays and nightstands...really, really, REALLY getting to know your co-workers!

It might just be too much to bear for most folks...but not us! As a way to let off a little steam, we had a cookout! Chicken, burgers, dogs, veggies, and salads, and Uncle Tim did the grillin' while we did the chillin'!


Monday, August 14, 2006

After a relatively uneventful Friday and weekend, we received some good news on Monday. At about 10:00 it was announced that ASC had secured a new temporary office space! ASC's new home for the next six months will be in Plaza South Two, right next door to our old office. The office contains about 9,500 square feet of space, 70 furnished and wired cubicles, a conference room, kitchen, server room and four small offices.

By noon, a crew was busy at work, moving, cleaning and preparing the new office. Shortly thereafter, the entire 'ASC South' hotel headquarters was shut down, dismantled, and moved. The IT staff worked long into the night re-establishing the servers, connecting cubicles and generally doing everything to get us up and running the next day.


Tuesday, August 15, 2006

About 25 ASC employees reported for work on Tuesday morning at the new office space. By the time they arrived, most of the servers were running and connection to assigned cubicles were made. Those with laptops and cleaned PCs hooked up and went to work.

Most of the web services were up and running by 3:00 pm. This included all of our web sites, Wiki, Internet E-mail, Web Mail, and FTP sites.

We received our phone system and most remaining servers, PCs monitors and related equipment back from the cleaning service beginning at about 4:00 pm.
It will be, however, at least another five to seven business days before the phone company can move our existing lines to this new location. Temporarily, three cordless phones were installed throughout the suite for making outgoing calls. Our fax machine was re-installed. The number is: (440) 243-4369.

Welcome to ASC

 

Wednesday, August 16, 2006

More workers arrive at ASC and return to a regular environment. Our server rack returns and quickly gets filled with sweet smelling servers who just had a bath and week's vacation. It is not known whether ASC personnel received the same treatment! LOL! Nearly everyone has a PC with which to work.


Thursday, August 17, 2006

Another delivery of cleaned electronics is scheduled for delivery later this afternoon. We hope to get back all the remaining PCs and some miscellaneous equipment.

Two database servers, Darwin and Hopper are experiencing problems. We do not know if the problems are related to the smoke damage, the cleaning process or us moving them so many times. We're moving data off the servers and are sending them back to be checked out. If the cleaning service cannot resolve the problem then we will make an insurance claim. The same goes for our other hardware (workstations, monitors, phones, printers).

Coffee makers arrive as does a brand new refrigerator! Life is...getting better anyway!


Friday, August 18, 2006

A professional cleaning service will begin packing up our belongings in our damaged office on Monday for cleaning. Everything must go in order for repairs and rebuilding to proceed. Everything not designated for cleaning will be thrown out. All records are being sealed, cleaned and stored.

Individuals stare in amazement at how much stuff they accumulated in a single office or cubicle over a career. Mugs, paper clips, photos, children's artwork, post-it notes, receipts, loose change, CDs, diskettes, files, folders, papers, papers, and more papers. Our collective guess is that cubicles and offices in the new space will remain quite Spartan.


Monday, August 21, 2006

We arrive this Monday with a renewed crease in our pants as casual dress days come to an end. This gesture symbolizes the we are truly back on our feet and are ready to make up for lost time.

The alarm system in our new suite is installed. Everyone awaits the arrival of the phone system!

The cleaning service arrived and will begin clearing out items from the suite. Their job is mainly to separate items to be cleaned, claimed for insurance or tossed out. No less than eight individuals will work through the week on this task.


Tuesday, August 22, 2006

Limited phone service is restored along with some of our printers. The security system in the new suite is being reprogrammed, and is ready for use.


Wednesday, August 23, 2006

The phone system is restored in full, including outgoing long distance and voicemail. The internal security systems are being restored as well, so we're essentially as secure as we were the day of the fire.


Thursday, August 24, 2006

A core group of ASC employees has had the ongoing task of sorting, tagging, and removing items from the old office. As the cleaning service brought forth items for consideration, the ASC folks had to coordinate their removal. As you can see from the photos, this has been an overwhelming endeavor. At the end of the day Thursday, ASC is void of all work contents. Crews began dismantling cubicles and removing all the furniture.

Support
Training Room
Product Development
Tagged Stuff
Furniture goes away for cleaning and storage
Renovation Begins
 
Our New Home (for the next six months)
 

Friday, August 25, 2006

Almost four weeks after the fire, ASC's suite is empty and ready for a complete teardown. All interior walls, wall coverings, ceiling tiles, overhead wiring and floor coverings will be removed. This process is nearly complete on the floor above us and the floor below us where the fire originated.


Tuesday, September 19, 2006

A brief update on the goings-on at ASC, chiefly security. We have made great stride in securing our new premises.

For example, our suite is now equipped with an keyless entry system to control access during business hours. For off hours, we have installed an alarm system complete with web-cameras and a smoke and fire detection system.

We have monitoring systems in place to track all traffic in and out of the premises.

Our wiring, telephone and Internet closet is secured with a secondary alarm.

We ordered modular walls and a door to secure the server room. This is due to be delivered this week.


Friday, September 29, 2006

Demolition continues on our old building, but there is hope, as seen in this image, that things are looking up for ASC!.

 

April - July 2007

Work resumes on Plaza South One after a Winter hiatus. Crews begin by removing windows and storing them onsite. Next massive moveable scaffolding is installed. Within weeks, crews begin removing the brick facade from the building. Within a few short months, all four sides have been stripped and re-bricked. By early July, the windows have been reinstalled. Work on the interior contiuned throughout this time. A temporary concrete mixing operation was constructed in the back parking lot so that structural repairs could be made.

Rough plans have been reviewed by ASC for revamping our old office footprint to make better use of space.

Below are a series of images from the process described above. In mid-June, ASC was invited inside to see the progress (or lack thereof) on our old office. Images of this visit are included as well.

Scaffold installation
Brick Removal Begins
One Side Done
Brick Removal
ASC Still Stands!
Customer Support Area
Programmers Hard at Work!
Wires Everywhere!

Monday, July 30, 2007 - ONE YEAR LATER

We noted the passing of one year since the fire which displaced us from our offices. It's been very quiet the past 9 months or so, but looking back to last August, it was pretty crazy!

Below is a recent photo of the building. As you can see, the exteior work has been essentially completed. Build-out of actual office spaces will begin soon.


September 12, 2007

Renovation is nearing completion on our suite. The majority of the walls are in place and the entire office has been primed for paint. The floor is ready for carpet as well. Dave & Joe have been busy removing the many generations of old PC wiring, and are preparing the area for new cable. No definative word on when we're moving, but our suite is getting closer to being done! ~More to come.

ASC Lobby
Entryway Looking Out
Conference Room
Admin / Sales Area
Offices
Training
Kitchen
Library / Storage
Product Development
Looking Toward Prod Dev
Wire removal in Customer Support area
Server Room

December 2007

As we prepare for an early January move-in date, our suite is progressing nicely. But will it be done in time?

Administration/Lobby
Main Hallway
Lunchroom
Product Development
Wires! (The First of Many)
Support

Monday, January 7, 2008

ASC resumes operation in our offices, following 18 months in a temporary location following the fire. Although it's still noisy, dusty and full of boxes, we're back home where we belong. Here are some photos from the first few days.

Lobby
Support
Support
Training Room (Classes start in February!)
Product Development
Our New Kitchen

We would like to thank all of our clients for their patience and understanding throughout the past 18 months. We worked hard to maintain our high level of customer service during our 'crisis'. We are also thankful to our employess and especially to ASC Management for providing support and leadership through it all.

It is amazing, but not surprising, how this incident exposed the character and dedication of the ASC family. We have high expectations for this year, and we wish you all a prosperous 2008 as well.